米拉多大型铜矿排土场工程优化研究与实践

周生,杨承祥,胡慧曙,陈平,雷丁丁,李广泽,蒋蔚   

  1. 铜陵有色金属集团控股有限公司,安徽 铜陵 244000
  • 出版日期:2018-10-15 发布日期:2018-11-09

Research and Practice on Optimization of Waste Dump Engineering of Mirador Copper Mine

Zhou Sheng,Yang Chengxiang,Hu Huishu,Chen Ping,Lei Dingding,Li Guangze,Jiang Wei   

  1. TongLing Nonferrous Metals Group Holdings Co., Ltd.,Tongling 244000,China
  • Online:2018-10-15 Published:2018-11-09

摘要: 简述了米拉多大型铜矿排土场、截水沟和酸性水库等采矿工程设计优化方案。从工程施工工期、投资、生产运营成本、安全环保等方面,定性定量地分析和比较优化方案与原方案的优缺点。根据优化后的排土场、截水沟和酸性水库等采矿工程方案,南北截水沟总长度减少近3 km,土石方量减少约30%,截水沟钢筋混凝土量减少约20%,投资减少21%以上;南北矿总酸性水库3个减少为2个;采场废石运距平均缩小1 km。通过施工实践,南矿排土场优化方案比原初步设计大排土场方案基建期投资节省2 689万美元以上,南北矿排土场总体服务年限内投资减少3 121万美元,运营成本少5 100万美元,酸性水处理量每天减少约9 000 m3,减少年运营成本约300万美元。优化方案为海外矿山建设提供了成功的范例。

关键词: 米拉多铜矿, 排土场, 截水沟, 方案优化, 实践

Abstract: The engineering design optimization schemes for the dump, ditch and acidic reservoir of the Mirado copper mine are briefly described. The merits and demerits of the optimized scheme are qualitatively and quantitatively analyzed and compared with that of the original scheme from the aspects of construction period, investment, production and operation cost, safety and environmental protection. According to the optimized mining projects in dump, ditch and acidic reservoir, the total length of the north-south ditch is shortened by nearly 3 km, the amount of earth and rocks is reduced by about 30%, the amount of reinforced concrete in ditch is lowered by about 20%, and the investment is cut by more than 21%; Three total acidic reservoirs in the north and south mines is reduced to two; The average transportation distance of waste rock in stope is shortened by 1 km. Through the construction practice, the optimized scheme of the dump in south mine saves more than 26.89 million US dollars in the capital construction period than the original preliminary design scheme. The investment within the overall service life of the dump in North and South Mines is reduced by 31.21 million US dollars, with the operation cost reduced by 51 million US dollars, the acid water treatment capacity reduced by 9,000 m3 per day, and the annual operation cost lowered by about 3 million US dollars. The optimized plan provides a successful example for overseas mine construction.

Key words: Mirador copper mine, Waste dump, Intercepting ditch, Scheme optimization, Practice