高峰矿独头巷道通风降温参数优选及现场应用

黄世顶1 刘 尧2 邓红卫2 余汝海3 朱龙辉4 郁新国1   

  1. 1.华锡集团广西高峰矿业有限责任公司,广西 河池 547205;2.中南大学资源与安全工程学院,湖南 长沙 410083; 3.湖南安标检验认证有限公司,湖南 长沙 410118;4.湖南煤矿安全监察局安全技术中心,湖南 长沙 410119
  • 出版日期:2026-07-15 发布日期:2026-08-24
  • 通讯作者: 邓红卫(1969—),男,教授,博士,博士研究生导师。
  • 作者简介:黄世顶(1988—),男,工程师。
  • 基金资助:
    国家自然科学基金项目(编号:51874352)。

Optimization and Field Application of Ventilation and Cooling Parameters of Single-head Roadway in Gaofeng Mine

HUANG Shiding 1 LIU Yao2 DENG Hongwei2 YU Ruhai3 ZHU Longhui4 YU Xinguo1   

  1. 1.Sinotin Group Guangxi Gaofeng Mining Co.,Ltd.,Hechi 547205,China;2.School of Resources and Safety Engineering, Central South University,Changsha 410083,China;3.Hunan Standard Inspection and Certification Co.,Ltd., Changsha 410118,China;4.Safety Technology Center,Hunan Coal Mine Safety Supervision Bureau,Changsha 410119,China
  • Online:2026-07-15 Published:2026-08-24

摘要: 针对高峰矿深部开采区域掘进工作面的高温问题,矿山拟采用局部通风方式对其进行降温。在进行通 风降温之前,需要选取合适的通风降温参数确保工作面能够实现良好的降温效果。采用数值分析与现场试验相结合 的方式,设计了包含不同风筒直径、送风温度、送风速度和风流进口与工作面距离等通风参数的正交试验。通过数值 模拟计算分析出独头巷道区域在不同通风参数下的降温效果,并利用极差分析方法优选出最佳通风降温参数。在此 基础上进行了现场试验,并将现场实测的巷道空气温度与数值模拟计算结果进行了对比分析。结果表明:不同通风 方案下的独头巷道内空气温度均有明显降低,且巷道围岩温度呈现出阶梯状的分布特征。出风口平均温度和巷道内 空气的平均温度均随着时间步数叠加逐渐降低。最佳通风降温参数设计为:风筒直径600 mm、送风温度18 ℃、送风 速度6 m/s和风流进口与工作面距离20 m。基于最优通风参数的现场试验实测结果与数值分析结果较为接近,相对 误差不超过10%,说明采用数值分析方法能够为矿山独头巷道降温提供可靠的理论依据。

关键词: 深部开采 , 矿井通风 , 通风参数优选 , 数值分析 , 正交试验 , 现场应用

Abstract: To address the high-temperature issue at the heading face in the deep mining area of the Gaofeng Mine,local ventilation was adopted for cooling purposes.Prior to implementing ventilation cooling,it was necessary to select appropriate ventilation parameters to ensure effective cooling performance.A combined approach of numerical analysis and field experi ments was employed,and an orthogonal experimental design was developed,incorporating parameters such as duct diameter, supply air temperature,supply air velocity,and the distance between the air inlet and the working face.Numerical simulations were conducted to evaluate the cooling effects under different ventilation parameters in the blind heading,and range analysis was applied to identify the optimal combination.Subsequently,field tests were carried out based on the optimized parameters, and the measured air temperatures in the roadway were compared with the numerical simulation results.The results indicate that under all ventilation schemes,the air temperature in the blind heading decreased significantly,and the surrounding rock temperature exhibited a stepped distribution.Both the average temperature at the air outlet and the average air temperature in the roadway gradually decreased with increasing time steps.The optimal ventilation parameters were determined as follows:duct diameter of 600 mm,supply air temperature of 18 ℃,supply air velocity of 6 m/s,and distance between air inlet and working face of 20 m.The field test results obtained with the optimal parameters agreed well with the numerical predictions,with rela tive errors not exceeding 10%.This demonstrates that the numerical analysis method can provide a reliable theoretical basis for cooling blind roadways in mines.

中图分类号: