露天地下协同采矿充填方法

任凤玉,张东杰,李海英,宋德林   

  1. 东北大学资源与土木工程学院,辽宁 沈阳 110189
  • 出版日期:2015-03-15 发布日期:2015-07-31

An Approach of Open-pit and Underground Cooperative Mining and Filling

Ren Fengyu,Zhang Dongjie,Li Haiying,Song Delin   

  1. College of Resources and Civil Engineering,Northeastern University,Shenyang 110189,China
  • Online:2015-03-15 Published:2015-07-31

摘要: 针对弓长岭铁矿东南区低品位铁矿床平行矿带条件、高落差开采引起的地表塌陷区控制需求,分析了用常规充填法控制地表岩移所面临的产能低与经济效益差等问题,研究了塌陷坑内散体对实体边壁的控制作用,提出了利用临界散体柱原理控制地表塌陷范围的新型充填方式;试验研究了移动散体的结拱条件,揭示了塌陷坑内散体流动的连续性,得出向塌陷坑充填废石不会发生结拱陷落危害的结论;观测分析了塌陷坑壁面的构成,揭示了两帮围岩主要沿结构弱面向塌陷坑片落或滑落的特性,据此提出了沿塌陷坑轴向、径向协同排放废石以防治边壁滑落危害的安全充填技术;此外,地下采用大结构参数无底柱分段崩落法开采,在增大开采强度的同时均衡塌陷坑散体的下降速度,形成了露天地下协同采充方法。理论分析与工业试验表明,该方法可大幅度提高采充生产效率和改善采充作业环境,为急倾斜平行矿带低品位铁矿床环保型高效开采开辟了新途径。

关键词: 协同开采, 地表塌陷, 临界散体柱, 采矿充填

Abstract: According to the conditions of parallel belt at low-grade iron ore deposits in southeast area of Gongchangling Iron Mine and control requirements of surface subsidence area caused by high drop mining,the problems of the low productivity and poor benefit created by using conventional cut filling method are analyzed to control surface rock movement,the control action of granular in collapse pit to the solid side wall is studied,and a new filling approach for controlling the range of the surface subsidence by using the critical medium column theory is proposed.In the paper,the arch conditions of moving granular is studied on trial,which reveals the continuity of granular flow in collapse pit,and draws the conclusion that filling waste rock into collapse sink would not cause arch and fall hazard.The composition of collapse pit wall is observed and analyzed to reveal the characteristics that the surrounding rocks slide or chip mainly along the weak structural plane,and accordingly safety filling measures that the filling waste cooperative emissions along the collapse pit axial and radial is put forward to prevent side wall slipping;In addition,the large structural parameters sublevel caving is adopted for underground to increase mining intensity and balance the decline rate of granular in collapse pit,which forms the open-pit and underground cooperative mining and filling methods.It is proved by theoretical analysis and industrial experiments that the method above can enhance production efficiency and improve the working environment largely,and create an environmental protection and high efficient mining approach for the steep iron deposits with low-grade parallel belt.

Key words: Cooperative mining, Surface subsidence, Critical medium column, Mining and filling technology