金属矿山 ›› 2015, Vol. 44 ›› Issue (12): 38-41.

• 采矿工程 • 上一篇    下一篇

松散地层中水平巷道快速掘进施工法

李月先1,沈艳忱1,张冠洲2,陈卓3,4,赵普山5,郭静明6   

  1. 1.南京水利科学研究院,江苏 南京 210029; 2.解放军理工大学国防工程学院,江苏 南京210007;3.解放军理工大学野战工程学院,江苏 南京210007;4.71887部队,山东 烟台 265800;5.南京军区司令部,江苏 南京 210007;6.解放军65587部队,吉林 四平136001
  • 出版日期:2015-12-15 发布日期:2016-03-09

Horizontal Tunnel Rapid Excavation Construction Method in Loose Formation

Li Yuexian1,Shen Yanchen1,Zhang Guanzhou2,Chen Zhuo3,4,Zhao Pushan5,Guo Jingming6   

  1. 1.Nanjing Water Resources Research Institute,Nanjing 210029,China;2.College of Defense Engineering,PLA University of Science and Technology,Nanjing 210007,China;3.College of Field Engineering,PLA University of Science and Technology,Nanjing 210007,China;4.No.71887Troops of PLA,Yantai 265800,China;5.Headquarters of Nanjing Military Region,Nanjing 210007,China; 6.No.65587 Troops of PLA,Siping 136001,China
  • Online:2015-12-15 Published:2016-03-09

摘要: 为解决松散地层中水平巷道非施工支护的快速施工理论和施工工艺及操作方法,对松散地层中双排双层长距离输水地涵快速施工的案例进行了深入的分析,依据顶管管周的摩擦阻力、迎面阻力和顶管管段的自重等,研究了适用于松散地层中金属矿山水平巷道顶管快速施工的顶力计算和新的施工工艺、技术,并进行现场试验和各项监测,还对实测顶力与3种计算数值进行对比分析,将快速掘进施工法与钻孔爆破施工支护法进行了有关技术经济指标的对比分析,验证了快速掘进施工法的先进性、可行性和适用性。

关键词: 松散地层, 快速掘进, 顶管施工, 顶力计算, 现场试验

Abstract: In order to grasp the rapid construction theory and construction technology and operation method of non-construction supporting of horizontal tunnel in loose strata,a thorough analysis on the rapid construction case of the double rows-double layers long distance water diversion culvert in loose formation was made.Based on the friction around jacking pipe,face pressure and the self weight of the pipeline,the jacking force calculation and the new construction process and technology for rapid tunnel construction of metal mines horizontal tunnel in loose formation were acquired.An in-site jacking experiment and various monitoring were carried on and the measured jacking force was contrasted with the three calculated values.The comparison of the relevant technical and economic indicators between the rapid excavation and construction method and the construction supporting method verified the progressiveness,feasibility and applicability of the rapid excavation construction method.

Key words: Loose formation, Rapid excavation, Jacking construction, Jacking force calculation, In-site experiment