金属矿山 ›› 2017, Vol. 46 ›› Issue (10): 176-178.

• 采矿工程 • 上一篇    下一篇

直排尾矿固化回填梅山铁矿地表塌陷坑试验研究

吴荣高1,刘海林2,3 ,孙国权2,3 ,王星2,3   

  1. 1.南京梅山冶金发展有限公司矿业分公司,江苏 南京 210041;2.中钢集团马鞍山矿山研究院有限公司,安徽 马鞍山 243000;3.金属矿山安全与健康国家重点实验室,安徽 马鞍山 243000
  • 出版日期:2017-10-15 发布日期:2017-10-15

Curing and Backfilling Test of Surface Subsidence Pit by Directly Discharging Tailings in Meishan Iron Mine

Wu Ronggao1,Liu hailin2,3,Sun Guoquan2,3,Wang Xing2,3   

  1. 1.Mining Branch,Nanjing Meishan Metallurgy Development Co.,Ltd.,Nanjing 210041,China;2.Sinosteel Maanshan Institute of Mining Research Co.,Ltd.,Maanshan 243000,China;3.State Key Laboratory of Safety and Health for Metal Mines,Maanshan 243000,China
  • Online:2017-10-15 Published:2017-10-15

摘要: 为了解决尾矿库库存不足和地下崩落法采矿引起的地表塌陷坑所带来的土地浪费和安全隐患问题,梅山铁矿拟将尾矿分级浓缩后添加固化剂直接向地表塌陷坑内堆存。由于地下采矿活动在继续,塌陷坑处于活跃状态,尾矿固化堆存后,会引起崩落法开采的覆盖层构成发生变化。为此,通过对覆盖层的安全结构特性和安全堆存技术进行相应的相似模拟试验研究,摸索出了尾矿固化充填塌陷坑后一些规律,对矿山工程实施具有重要意义。

关键词: 尾矿直排固化, 塌陷坑回填, 物理模拟

Abstract: In order to solve the problems of the insufficient shortage of tailings pond and the land waste and hidden trouble caused by the surface subsidence pits caused by the underground mining activities by adopting caving mining method,the surface subsidence pit is processed by directly charging the tailings that is conducted grading enrichment and curing agent adding in Meishan Iron Mine.As the underground mining activities continues,the subsidence pit is the active state,the stratigraphic structure of the coverage layer of caving mining method is changed after curing and stockpiling of tailings.Some regularities of the surface subsidence pit after conducting tailing curing and backfilling are discussed based on the similar simulation test of the safety structural characteristics of coverage layer and safety stockpiling technology.The above analysis results of this paper has important significance for mining engineering.

Key words: Tailings straight ossification, Backfilling of subsidence pit, Physical simulation