金属矿山 ›› 2023, Vol. 52 ›› Issue (03): 73-79.

• 采矿工程 • 上一篇    下一篇

基于数码电子雷管的准楔形复式掏槽爆破试验研究

王雁冰1 鲍舟琦1 谢 平2 张英豪3 王国豪1
  

  1. 1. 中国矿业大学(北京)力学与建筑工程学院,北京 100083;2. 淮浙煤电有限责任公司顾北煤矿,安徽 淮南 232150;3. 北京煋邦数码科技有限公司,北京 102308
  • 出版日期:2023-03-15 发布日期:2023-04-12
  • 基金资助:
    “十四五”国家重点研发计划项目(编号:2021YFC2902103);国家自然科学基金重点项目(编号:51934001);中国矿业大学(北京)越崎 青年学者资助项目(编号:800015Z11A24)。

Experimental Study of Quasi Wedge Compound Cut Blasting Based on Digital Electronic Detonator

WANG Yanbing1 BAO Zhouqi1 XIE Ping2 ZHANG Yinghao3 WANG Guohao1   

  1. 1. School of Mechanics and Civil Engineering,China University of Mining and Technology-Beijing,Beijing 100083,China;2. Gubei Coal Mine,Huaizhe Coal and Electricity Co. ,Ltd. ,Huainan 232150,China;3. Beijing Sino Bang Technology Co. ,Ltd. ,Beijing 102308,China
  • Online:2023-03-15 Published:2023-04-12

摘要: 针对目前掏槽爆破中爆破效果不够理想、单循环时间较长等问题,于顾北矿北-1 煤顶板轨道上山第三 中部车场进行爆破试验,对原始爆破方案进行改进,并优化爆破参数。 首次在井下岩巷掘进中引入数码电子雷管,用 数码电子雷管代替煤矿许用普通电子雷管,增加爆破段别。 根据岩石巷道现场情况,利用数码电子雷管能够任意设 置爆破段别延期时间的优点,设计了 2 种准楔形复式掏槽爆破新方案。 将 3 种方案的爆破效果进行了对比,发现炮孔 利用率提高至 96. 1%,单循环进尺增加到 1. 78 m,在原方案的基础上提升了 12. 8%。 结果表明:数码电子雷管的可靠 性较高,并初步确定了炮孔利用率最高时的爆破段别延期时间。 岩巷掘进中使用数码电子雷管,能够使爆破过程可 控,除了掏槽孔外的其他炮孔有充分的爆破空间,增加单循环进尺,减少单循环时间,提升巷道成型质量,提高工作效 率,具有良好的经济社会效益。

关键词: 矿山爆破, 岩巷掘进, 钻爆法, 数码电子雷管, 炮孔利用率

Abstract: Aiming at the problems such as unsatisfactory blasting effect and long single cycle time in the current cut blasting,the blasting experiment was carried out in the third middle yard of horth-1 coal roof track in Gubei Mine,the original blasting scheme was improved and the blasting parameters were optimized. The digital electronic detonator is introduced for the first time in the underground rock tunneling,and the digital electronic detonator is used to replace the common electronic detonator permitted in coal mine,and the blasting section is increased. According to the field situation of rock roadway,two new quasiwedge compound cut blasting schemes are designed by using the advantage that digital electronic detonator can arbitrarily set the delay time of blasting section. By comparing the blasting effects of the three schemes,the utilization rate of borehole is improved to 96. 1%,and the single-cycle footage is increased to 1. 78 m,which is 12. 8% higher than the original scheme. The results show that the reliability of digital electronic detonator is high,and the delay time of blasting section is preliminarily determined when the utilization rate of borehole is the highest. The use of digital electronic detonator in rock tunneling can make the blasting process controllable,have sufficient blasting space except the cut hole,increase the single cycle footage,reduce the single cycle time,improve the quality of tunnel forming,improve the work efficiency,and have good economic and social benefits.