金属矿山 ›› 2023, Vol. 52 ›› Issue (07): 153-158.

• “矿井粉尘智能防控理论及新技术进展”专题 • 上一篇    下一篇

矿用局部通风机风量补给及测定组合装置研发及应用

周 伟1,2 李 刚1,2 贾敏涛1,2 吴冷峻1,2 纪旭波3 林喜村3 谢 辉1,2 余茂杰4
  

  1. 1. 金属矿山安全与健康国家重点实验室,安徽 马鞍山 243000;2. 中钢集团马鞍山矿山研究总院股份有限公司,安徽 马鞍山 243000;3. 山东恒邦冶炼股份有限公司,山东 烟台 264000;4. 铜陵有色金属集团控股有限公司,安徽 铜陵 244000
  • 出版日期:2023-07-15 发布日期:2023-09-05
  • 基金资助:
    “十四五”国家重点研发计划项目(编号:2022YFC2904104);金属矿山安全与健康国家重点实验室开放基金项目(编号:2021-JSKSSYS-06)。

Development and Application of Combined Device for Air Volume Replenishment and Measurement of Mine Local Ventilator

ZHOU Wei1,2 LI Gang1,2 JIA Mintao1,2 WU Lengjun1,2 JI Xubo3 LIN Xicun3 XIE Hui1,2 YU Maojie4 #br#   

  1. 1. State Key Laboratory of Safety and Health for Metal Mines,Maanshan 243000,China;2. Sinosteel Maanshan General Institute of Mining Research Co. ,Ltd. ,Maanshan 243000,China;3. Shandong Humon Smelting Co. ,Ltd. ,Yantai 264000,China;4. Tongling Nonferrous Metals Group Holdings Co. ,Ltd. ,Tongling 244000,China
  • Online:2023-07-15 Published:2023-09-05

摘要: 掘进作业中产生的粉尘若不能及时地稀释并排出,容易形成积聚现象,对作业人员的身体健康造成极 大的危害。 研发了一种适合于金属矿山矿用局部通风机风量补给及测定组合装置,并在山东省某金矿-300 m 水平探 矿穿脉独头作业面进行了试验。 结果表明:引入该装置后,随着掘进作业推进,在不变更原局部通风机台数和型号的 情况下,通过对风筒内的风压和风量进行可控式补偿,作业面排尘风速始终维持在 0. 36 m / s 左右,满足《金属非金属 矿山安全规程》(GB 16423—2020)的相关通风设计要求。 该装置实现了局部通风机风量补给和测定一体化,较好地 解决了因掘进距离变长、通风阻力增大造成经柔性风筒送达工作面风量减小以及风量测定安全性低、精准度差的问 题,对于改善井下作业环境、保障金属矿山独头掘进安全生产具有重要意义。

关键词: 矿井通风, 局部通风机, 风量补给, 风压测定, 输出风量

Abstract: If the dust generated during excavation operations cannot be diluted and discharged in a timely manner,it is easy to accumulate and cause great harm to the physical health of the workers. A combined device for supplying and measuring the air volume of local ventilation fans suitable for metal mines has been developed and tested on a -300 m horizontal exploration single end mining face in a gold mine in Shandong Province. The test results show that after the introduction of this device, as the excavation operation progresses,without changing the original number and model of local ventilation fans,the dust exhaust wind speed of the working face is always maintained at around 0. 36 m / s by controllable compensation of the air pressure and air volume in the air duct,meeting the relevant ventilation requirements of the Safety Regulations for Metal and Non-metal Mines (GB 16423-2020). This device realizes the integration of local ventilation fan air supply and measurement,effectively solving the problems of reduced air volume delivered to the working face through flexible air ducts due to longer excavation distance and increased ventilation resistance,as well as low safety and accuracy of air volume measurement. It is of important significance for improving the underground working environment and ensuring the safety production of metal mine single head excavation.

Key words: mine ventilation,local ventilator,air supply,wind pressure measurement,output air volume