头石山尾矿坝的动力液化分析

张进1,2,乐陶1,2,曹纪刚1,2   

  1. 1.中钢集团马鞍山矿山研究院有限公司;2.金属矿山安全与健康国家重点实验室
  • 出版日期:2012-06-15 发布日期:2012-06-29

Dynamic Liquefaction Analysis of Toushishan Tailing Dam

Zhang Jin1,2,Yue Tao1,2,Cao Jigang1,2   

  1. 1.Sinosteel Maanshan Institute of Mining Research Co.,Ltd.;2.State Key Laboratory of Safety and Health for Metal Mine
  • Online:2012-06-15 Published:2012-06-29

摘要: 头石山尾矿库是一个拟建的新库,其等级按规范要求确定为二等库,且该库处于8度地震区,其动力稳定性应值得重视。对该尾矿库在某一地震波作用下进行了动力液化的计算与分析,为尾矿坝在高烈度地震区的设计及管理提供参考依据。

关键词: 尾矿坝, 地震, 动力液化

Abstract: The Toushishan tailing bond is a proposed new tailing bond, and according to specification requirements, its level identified as second class tailing pond. The tailing pond is in 8 degrees in quake zone, and its dynamic stability should be paying attention. The Toushishan tailings in a seismic dynamic liquefaction under the action of the calculation and analysis was calculated and analyzed. It can provide the reference for tailings dam in high intensity earthquake region design and management.

Key words: Tailing dam, Earthquake, Dynamic liquefaction