Ground Pressure Distribution and Control of the Stope Based on Combined Mining in Chengchao Iron Mine

Zhang Kaixin,Wang Ping,Pei Mingsong,Jiao Ao,Wang Chuang,Shang Huandi   

  1. School of Resource and Environmental Engineering,Wuhan University of Science and Technology,Wuhan 430081,China
  • Online:2016-05-13 Published:2016-08-18

Abstract: With the combined mining of two methods for exploiting ore-body at -430 ~ -500 m stage of Chengchao Iron Mine as the engineering background,the pressure distribution and mining field stability problems of the stope under the combined mining method are explored.The excavation process of the ore body was simulated by numerical analysis software FLAC3D based on the finite difference theory.According to the simulation results,the stresses variation and safety factor of the stope before and after excavation and isolation pillar deformation were obtained.The control measures of underground pressure and the corresponding management system was provided as well based on the analysis results.

Key words: Combined mining, Numerical simulation, Stability, Ground pressure distribution, Ground pressure control