Study on Mining Technology of Pre-truncating Crest Disaster Isolation for Deep Orebody in Xiadian Gold Mine

Wang Jinbo1,He Shaobo1,Rao Yunzhang2,Zhou Dongliang1,Deng Hongwei3,Wang Bingwen4   

  1. 1.Xiadian Gold Mine,Zhaojin Mining Industry Co.,Ltd,Zhaoyuan 265400,China;2.School of Resources and Environment Engineering,Jiangxi University of Science and Technology,Ganzhou 341000,China;3.School of Resources and Safety Engineering,Central South University,Changsha 410012,China;4.School of Resources and Safety Engineering,China University of Mining and Technology(Beijing),Beijing 100083,China
  • Online:2016-06-15 Published:2016-08-19

Abstract: Aimed at mining conditions that the hanging wall of inclined thick deep orebody is existing fault gouge in Xiadian Gold Mine,now the main problems of high loss and dilution rate and hard surface protection were appeared with sublevel caving method used.The combination of present situation and mining conditions,the test scheme of pre-truncating crest disaster isolation mining was proposed.In the stope,the triangle ore of hanging wall was mined at first.Then the goaf was filled with high concentration and high cement-sand ratio of classified tailings to isolate the disaster body at hanging wall with poor stability.In the ore block,the pillar was mined in advance,and the goaf was filled by high strength cemented tailings.Then the room was mined,and filled by low strength cemented tailing or hydraulic sands.The tests has indicated that the scheme can better control ground pressure,decrease the loss and dilution of ore,and increase the production capability to achieve the targets of safety,efficiency and low costs in mining of deep orebody.

Key words: Mining method, Deep mining, Pre-truncating crest, Disaster isolation