金属矿山 ›› 2010, Vol. 39 ›› Issue (07): 26-30.
• 采矿工程 • 上一篇 下一篇
魏建现
出版日期:
发布日期:
Wei Jianxian
Online:
Published:
摘要: 针对李楼-吴集铁矿联合建设工程原实施方案在开采顺序、开拓工程、采矿方法、通风系统、中段运输水平及运输系统、生产辅助设施和生活服务设施等方面存在优化潜力,在原实施方案基础上,通过对以上几个方面进行分析、研究与优化,使整个生产系统更加完善、合理,大幅度减少了基建工程量,加快了施工进度,缩短了建设工期,降低了基建投资和生产运营费用,补充完善了生产和生活服务设施,为生产顺利进行和企业发展提供了保障。
关键词:  , 联合建设, 实施方案, 开拓工程, 优化
Abstract: In view of its optimization potentiality in mining sequence, development project, mining methods, ventilation system, intermediate section transport level and transportation system, production subsidiary facilities and service facilities in original implementation plan of joint construction of Lilou-Wuji iron mine. The whole production system become perfect and more reasonable through analysis, research and optimization from above aspects based on the original implementation plan. By this way, the infrastructure construction is obviously shortened, meanwhile construction schedule speeded up, construction period shortened, and the investments and manufacturing costs reduced. The adequate production and service facilities provide a guarantee for the smooth production and business development.
Key words: Joint construction, Implementation plan, Development project, Optimization
魏建现. 李楼-吴集铁矿联合建设工程实施方案优化研究[J]. 金属矿山, 2010, 39(07): 26-30.
WEI Jian-Xian. Optimization of Implementation Plan of Joint Construction Project of Lilou Wuji Iron Mine[J]. Metal Mine, 2010, 39(07): 26-30.