Forecast of the Unit Explosive Consumption for Blasting in Open-Pit Iron Mine

Li Zhanjun,Wen Jianqiang,Zheng Bingxu   

  1. Guangdong Hongda Blasting Co., Ltd.
  • Online:2009-07-15 Published:2011-04-26

Abstract: With the forecast practice of the unit explosive consumption for blasting in an open-pit iron mine, the forecast method and calculation method by Kuznetsov and Rosin-Rammler mathematical model at a given boulder yield are presented.Evaluation and suggestions are made on the optimization of blasting parameters of open-pit blasting by the said model based on the practical experience.

Key words: Open-pit mine, Blasting, Boulder yield, Unit explosive charge