Research and Practice of Water Inrush Treatment in Tieshan Mine

Liu Shenglei,Wang Bing   

  1. Shandong Jinling Iron Mine
  • Online:2013-03-15 Published:2013-04-16

Abstract: According to the different hydrogeological conditions and the corresponding requirement of construction,different technical measures are adopted to treat the underground water inrush.Aiming at the problems occurred during the process of water treatment,the corresponding measures are taken to reach water control effect for meeting the production needs,thus providing the corresponding construction experience and technical parameters for water treatment with the same or similar hydrogeological conditions.