金属矿山 ›› 2025, Vol. 54 ›› Issue (6): 212-220.

• 安全与环保 • 上一篇    下一篇

基于解耦 Newmark 法与代表性滑动面的扩容尾矿坝 动力稳定可靠度分析 

徐  亮  李  亮  李春立  文嘉辉  王  超    

  1. 青岛理工大学土木工程学院,山东 青岛 266520
  • 出版日期:2025-06-15 发布日期:2025-07-09
  • 通讯作者: 李  亮(1977—),男,教授,博士研究生导师。
  • 作者简介:徐  亮(1988—),男,博士研究生。
  • 基金资助:
    山东省自然科学基金项目(编号:ZR2023ME007);中国水科院科技成果转化基金专项(编号:GE121003A0032022);流域水循环模拟与 调控国家重点实验室自主研究课题项目(编号:SKL2022ZD05)。 

Reliability Analysis of Dynamic Stability of Expanded Tailings Dam Based on Decoupled Newmark Method and Representative Sliding Surface 

XU Liang  LI Liang  LI Chunli  WEN Jiahui  WANG Chao    

  1. School of Civil Engineering,Qingdao University of Technology,Qingdao 266520,China
  • Online:2025-06-15 Published:2025-07-09

摘要: 结合解耦 Newmark 法和代表性滑动面进行分析,提出了一种高效评价尾矿坝动力安全性能的方法。 该 方法通过精确选取代表性滑动面并计算其屈服加速度,结合响应面分析,构建了尾矿坝位移预测和动力失效概率的 分析方法。 将该方法应用于云南某扩容尾矿坝工程案例中,准确识别了不同扩容阶段的最易破坏区域,并分别计算 其在地震作用下的永久位移及动力失效概率。 计算结果表明,新库区扩容至初期坝顶,旧尾矿坝易深层破坏;扩容至 原尾矿坝 1 / 2 高,新旧坝均易浅层失稳;至原坝顶,新建坝易浅层破坏;扩容坝服役期安全,满足使用要求。 案例计算 结果验证了该方法在工程实践中的准确性和可靠性。 

关键词: 尾矿坝动力稳定  可靠度分析  Geostudio  Newmark 法 

Abstract: Combined with the decoupled Newmark method and the representative sliding surface,an efficient method for evaluating the dynamic safety performance of tailings dam is proposed. By accurately selecting the representative sliding surface and calculating its yield acceleration,combined with the response surface analysis,the analysis method of displacement prediction and dynamic failure probability of tailings dam is constructed. This method is applied to a case of an expansion tailings dam project in Yunnan Province. The most vulnerable areas in different expansion stages are accurately identified,and the permanent displacement and dynamic failure probability under earthquake action are calculated respectively. The calculation results show that the new reservoir area is expanded to the initial dam crest,and the old tailings dam is prone to deep damage. The expansion to the original tailings dam 1 / 2 high,the old and new dams are prone to shallow instability. To the top of the original dam,the new dam is easy to be damaged in shallow layer. The service period of the expansion dam is safe and meets the requirements of use. The case calculation results verify the accuracy and reliability of the method in engineering practice. 

Key words: dynamic stability of tailings dam,reliability analysis,Geostudio,Newmark method 

中图分类号: